Project
Åmål 6:50
Åmål SE3 BESS
Overview
Capacity4 MW
Energy8 MWh
StatusReady to build
Connection2025 Q1
Grid ownerVattenfall
Asset life25+ years
Connection fee1,4 M sek
Grid owner quote250.000 sek per year
Area3980,3 m2
Comment
the site is located 300 meters from the substation